The NE Code® requires bonding of all the non-current-carrying metal parts of the ___

The NE Code® requires bonding of all the non-current-carrying metal parts of the electrical-power distribution system of a building or other structure together with interconnection to the grounded service-_____________ conductor or other ____________________________ service conductor to form the ground-fault return path.

A) neutral; biased
B) neutral; neutral
C) none of the answers
D) biased; neutral

Show Answer

Answer:B