When installing a siphon it ___
a) must be perpendicular to the piping
b) must be dry
c) should be downstream of an inspectors’ test connection
d) should be first filled with water
e) shall be as close
Show Answer
Answer: D
When installing a siphon it ___
a) must be perpendicular to the piping
b) must be dry
c) should be downstream of an inspectors’ test connection
d) should be first filled with water
e) shall be as close
Answer: D