While performing the open-circuit antI short-circuit tests on a transformer to determine parameters the status of the low voltage (LV) and high voltage (HV) wiridings will be such that
A. in OC, LV is open and in SC HV is shorted.
B. in OC, HV is open and in SC LV is shorted.
C. in OC, LV is open and in SC LV is shorted.
D. In OC, HV is open and in SC HV is shorted.
Show Answer
Answer: B