To check the continuity of a fuse with the power on, two methods are available for taking voltage readings.
Which of the following is (are) true?
A) All of The answers
B) Both methods take a minimum of two voltage readings: one before and one after the fuse.
C) The line-to-ground method cannot be used unless the control or power circuit being protected by the fuse(s) is referenced to ground.
D) One method is referred to as line-to-line measurements. The other is referred to as line-to-ground measurements.
Show Answer
Answer:A