___ volts should be measured with the other test lead to the line side of the secondary control fuse

____________ volts should be measured with the other test lead to the line side of the secondary control fuse.

If the fuse is good, ____________ volts should also be measured from the load side of the fuse.

If ____________ volts are measured on the load side of the fuse, then the fuse is open.

A) 120; zero; 120
B) 120; 120; zero
C) zero; zero; zero
D) zero; 120; zero

Show Answer

Answer:B